Postby mmartric » Mon Feb 05, 2018 9:49 pm

Which of the following is included in the A201 General Conditions?

Field Order
Post bid modifications
Test Boring Logs
Bid Bond
mmartric
 
Posts: 31
Joined: Mon Aug 24, 2015 10:38 am

Re: A201 General Conditions

Postby anonymous283 » Wed Feb 07, 2018 1:05 pm

None?
anonymous283
 
Posts: 149
Joined: Thu Jan 11, 2018 2:02 pm

Re: A201 General Conditions

Postby Coach » Wed Feb 07, 2018 4:32 pm

Only one is mentioned in A201. You might want to read it.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: A201 General Conditions

Postby Sparky83 » Wed Feb 07, 2018 6:39 pm

Coach wrote:Only one is mentioned in A201. You might want to read it.

Don't take the exam unless you have....
Sparky83
 
Posts: 7649
Joined: Tue Dec 02, 2014 1:36 pm

Re: A201 General Conditions

Postby jbmadison » Mon Mar 26, 2018 2:45 pm

Hello,
I have read the A201 General Conditions document, taken notes and reviewed them but cannot answer this question. Can anyone shed light on the answer?
Thanks in advance!
jbmadison
 
Posts: 2
Joined: Mon Mar 26, 2018 2:43 pm

Re: A201 General Conditions

Postby Coach » Mon Mar 26, 2018 9:48 pm

1.1.1
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: A201 General Conditions

Postby jbmadison » Tue Mar 27, 2018 10:58 am

Got it, thank you. Change orders, Construction Change Directives, and a written order for minor change of work are all Post Bid Modifications. Seems obvious now...
jbmadison
 
Posts: 2
Joined: Mon Mar 26, 2018 2:43 pm