Sparky83 wrote:AIA B101
3.6.6.1 The Architect shall:
1. conduct inspections to determined the date or dates of Substantial Completion and the date of final completion.
2. issue Certificates of Substantial Completion
3. forward to the Owner, for the Owner's review and records, written warranties and related documents required by the Contract Documents and received from the Contractor, and,
4. issue a final Certificate of Payment based upon a final inspection indicating that, to the best of the Architect's knowledge, information, and belief, the Work complies with the requirements of the Contract Documents.
Coach wrote:http://aiad8.prod.acquia-sites.com/sites/default/files/2017-02/a201-2007%20commentary.pdf
anonymous283 wrote:But what I'm asking about is the nuances of how the substantial completion is determined not simply what the contracts say. But whatever I got it thanks.