CDS Section - Testing in a few days!

Building Section Vignette and Multiple Choice

CDS Section - Testing in a few days!

Postby dilwilli » Sat Aug 05, 2017 5:59 pm

Hello,
I test in a few days. Please take a look and let me know if I've missed anything.
Thank you!
Dillon
You do not have the required permissions to view the files attached to this post.
dilwilli
 
Posts: 36
Joined: Tue Feb 25, 2014 8:04 am

Re: CDS Section - Testing in a few days!

Postby dilwilli » Tue Aug 08, 2017 7:31 pm

Here is the section without the background for clarity.
I test Thursday morning so any comments would be greatly appreciated!
You do not have the required permissions to view the files attached to this post.
dilwilli
 
Posts: 36
Joined: Tue Feb 25, 2014 8:04 am

Re: CDS Section - Testing in a few days!

Postby thd7t » Wed Aug 09, 2017 5:25 am

Your non-rated wall should only go 6" above ceiling.
thd7t
 
Posts: 400
Joined: Mon Aug 22, 2016 1:23 pm

Re: CDS Section - Testing in a few days!

Postby dilwilli » Wed Aug 09, 2017 6:13 pm

Good catch. Thank you!
dilwilli
 
Posts: 36
Joined: Tue Feb 25, 2014 8:04 am

Re: CDS Section - Testing in a few days!

Postby Sfny » Wed Aug 30, 2017 12:54 pm

it looks like the space you allowed for the ducts and lighting for the Lab is not deep enough

confirm that you have added the correct numbers for clearances -
the joist duct and light space for the Lab is 20"+8"= 28" (2'-4")
the joist and deck assembly for the Lab is 32" + 4"- 36" (3'-0") total 5'-4" above 15'
Sfny
 
Posts: 34
Joined: Wed Aug 17, 2016 4:29 pm