CHANGES DURING DESIGN PHASES

CHANGES DURING DESIGN PHASES

Postby ArchiShark » Thu Jun 29, 2017 1:47 pm

Can anyone help me out with the process of client changes during the design phases. I'm guessing that any changes during a design phase that would change a major design item/element, that was already approved at end of a previous phase would trigger an additional service because the change is after client approval. OR is it only changes after design development phase approval that deserve an additional service charge? OR am I totally wrong in both cases. Please help testing soon July 26. Thanks :?:
ArchiShark
 
Posts: 87
Joined: Tue Feb 04, 2014 10:15 am

Re: CHANGES DURING DESIGN PHASES

Postby gbalaka » Thu Jun 29, 2017 4:21 pm

The simple answer to your question is that if the client changes the scope of work during the first three phases (thus changes the contract), that would entitle the Architect to additional compensation.

Doesn't matter if it's SD, DD or CD. The important thing is that the contract is changing.
gbalaka
 
Posts: 330
Joined: Fri Dec 19, 2014 9:27 pm

Re: CHANGES DURING DESIGN PHASES

Postby Coach » Thu Jun 29, 2017 4:27 pm

Look at the contract. Be sure to study the version with commentary.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: CHANGES DURING DESIGN PHASES

Postby ArchiShark » Fri Jun 30, 2017 5:34 pm

Will Do! Thank you for pointing me in the right direction coach.
ArchiShark
 
Posts: 87
Joined: Tue Feb 04, 2014 10:15 am

Re: CHANGES DURING DESIGN PHASES

Postby ArchiShark » Fri Jun 30, 2017 6:34 pm

Thanks Gbalaka, I see the repeated calls for client approvals now, B210 2.2.4, 2.2.7, 2.3.1, 2.3.3, 2.4.1. Helpful!