Postby uptownwanderer » Sun Aug 27, 2017 2:40 pm

Last pass before testing tomorrow.

Two questions:

1. Should I worry about the Lobby becoming a dead end corridor? In this solution, I reduced the depth to ensure it was less than 20' from the south wall to the corridor plain.
2.Is 3' clear required from the strike side of the south MP exit door? I have this corridor at 6' clear, but the strike side of the door leaves 2'-8" in this solution. Should this corridor be increased in width to accommodate 3' clear?

Any and all comments welcome!

Thanks.
You do not have the required permissions to view the files attached to this post.
uptownwanderer
 
Posts: 8
Joined: Sun Mar 08, 2015 6:36 pm

Re: BL Last Try TESTING TOMORROW

Postby Sparky83 » Mon Aug 28, 2017 4:38 am

uptownwanderer wrote:Last pass before testing tomorrow.

Two questions:

1. Should I worry about the Lobby becoming a dead end corridor? In this solution, I reduced the depth to ensure it was less than 20' from the south wall to the corridor plain. There is no such thing as a dead-end lobby.
2.Is 3' clear required from the strike side of the south MP exit door? I have this corridor at 6' clear, but the strike side of the door leaves 2'-8" in this solution. Should this corridor be increased in width to accommodate 3' clear? ADA is not in the code for this vignette.

Any and all comments welcome!

Thanks.

Looks like it works.