BL 2nd try

Interior Layout & Building Layout Vignettes

BL 2nd try

Postby trouble » Fri Apr 21, 2017 10:05 pm

comments?

BL02-L1-sm.jpg

BL02-L2-sm.jpg
You do not have the required permissions to view the files attached to this post.
trouble
 
Posts: 8
Joined: Mon Feb 06, 2017 11:27 pm

Re: BL 2nd try

Postby katiebnx » Tue Apr 25, 2017 6:19 pm

MP door and Lobby entrance door to exterior overlaps with building limit line. Shift building over to avoid overlapping.
Corridor on east (right) end is a bit too long - Try to relocate program to not create a dead-end corridor.
Doors should swing out from LRs into MP (unless otherwise directed to in program) - doors from corridor correctly swing in.
At the 2nd floor, make sure the corridor leading to the LM isn't longer than 20ft.
katiebnx
 
Posts: 1
Joined: Sun May 22, 2016 11:32 am

Re: BL 2nd try

Postby Sparky83 » Wed Apr 26, 2017 7:05 am

katiebnx wrote:MP door and Lobby entrance door to exterior overlaps with building limit line. Not an error.Shift building over to avoid overlapping. Not necessary.
Corridor on east (right) end is a bit too long - Try to relocate program to not create a dead-end corridor. Dead-ends are allowed as long as they do not exceed 20' in length.
Doors should swing out from LRs into MP Does not matter in this vignette.(unless otherwise directed to in program) - doors from corridor correctly swing in.
At the 2nd floor, make sure the corridor leading to the LM isn't longer than 20ft.
Sparky83
 
Posts: 7649
Joined: Tue Dec 02, 2014 1:36 pm


Return to SD - SCHEMATIC DESIGN

Who is online

Users browsing this forum: No registered users and 47 guests

cron