Ramp, Stair, & Roof Vignettes and Multiple Choice
by cccjjj000 » Sun Jan 21, 2018 8:56 am
Test tomorrow... Thanks!
You do not have the required permissions to view the files attached to this post.
-
cccjjj000
-
- Posts: 37
- Joined: Tue Jun 21, 2016 10:48 am
by rarchll » Sun Jan 21, 2018 10:24 am
Roof over exhibition hall should be split up evenly. It also looks like your clearstory isn't drawn within the center of the wall. I've also heard that hip roofs are not recommended. I would split the lower roof into two symmetrical gables.
Edit: also apply additional flashing between lower and upper roof.
-
rarchll
-
- Posts: 42
- Joined: Sat Jul 23, 2016 8:06 am
by Coach » Sun Jan 21, 2018 3:59 pm
Upper roof is too low.
Missing flashing.
Do not flash ridge.
Sheds and hips not recommended.
Place clerestory in wall.
Place pvents over fixture wall.
Why are there gutters on east side of upper roof and north?
-
Coach
- Site Admin
-
- Posts: 13249
- Joined: Wed May 23, 2012 2:08 am
by cccjjj000 » Sun Jan 21, 2018 4:41 pm
Thanks Rarchll and Coach! Need more work on it...
Does it take points off if roof elevation is drawn higher than the minimum needed? I watched Amber video and it suggests giving a bit extra.
-
cccjjj000
-
- Posts: 37
- Joined: Tue Jun 21, 2016 10:48 am
by Coach » Mon Jan 22, 2018 12:57 am
cccjjj000 wrote:Does it take points off if roof elevation is drawn higher than the minimum needed? I watched Amber video and it suggests giving a bit extra.
Nobody knows, but I would be precise.
-
Coach
- Site Admin
-
- Posts: 13249
- Joined: Wed May 23, 2012 2:08 am
Return to BDCS - BUILDING DESIGN & CONSTRUCTION SYSTEMS
Who is online
Users browsing this forum: No registered users and 36 guests