Project Calendar

Site Grading & Site Design Vignettes and Multiple Choice

Project Calendar

Postby mrclx » Sun Jun 10, 2018 3:33 pm

Read this on the Architect Exam Prep Study guide.

" Project Calendar : Number of Working Days x 7 (or 5) days a week= Calendar Days for Construction "

Is this correct? If so.. can someone direct me to more info on this subject to help me understand?


Thank you !
mrclx
 
Posts: 27
Joined: Wed Mar 05, 2014 3:39 pm

Re: Project Calendar

Postby Coach » Sun Jun 10, 2018 3:51 pm

I think what you're looking for is: (work days/5)7=calendar days. That assumes a 5-day work week.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Project Calendar

Postby mrclx » Sun Jun 10, 2018 7:22 pm

Thank you coach !
mrclx
 
Posts: 27
Joined: Wed Mar 05, 2014 3:39 pm