here's my solution for the alt. site program #3

Site Grading & Site Design Vignettes and Multiple Choice

here's my solution for the alt. site program #3

Postby Veronika » Fri Apr 20, 2018 5:23 pm

Using the below program, does anyone see any issues?? My big questions were if the amount of Plaza I show at the restaurant entry complies with their requirement of the restaurant opening directly onto the plaza. Also am I showing the added trees correctly to block the service drive and provide shade for the plaza? Any comments appreciated!

A developer plans to build an Office Tower, a Restaurant, and a Pedestrian Plaza on the site, with parking to serve the new buildings.

1. Locate the 4-story, 48 ft high Office Building close to Bentley Avenue.
· The main entrance shall be protected from winter winds by buildings and/or trees, as appropriate.

2. Locate the 2-story, 36 ft high Restaurant close to the pond.

3. Draw a 12,000 ft² Pedestrian Plaza.
· Locate the Pedestrian Plaza within the building limit lines so that the main entrance to Restaurant opens directly onto the Pedestrian Plaza.

4. The view of the service entrance on the Restaurant shall be blocked from the Pedestrian Plaza.
· The view of the Service Entrance shall be blocked by buildings and/or trees, as appropriate.

5. The Office shall have a view of the Pond.

6. The main entrance of the Restaurant must be visible from Academy Street.

7. The Pedestrian Plaza shall be shaded from noon sun
· Assume 45 degree solar angle.

8. Draw a total of 42 parking spaces.
· 38 standard (9 ft x 18 ft) parking spaces are required.
· 4 universally accessible (12 ft x 18 ft) parking spaces are required.
· Locate the universally accessible parking spaces within 100 ft of the main entrance of the Restaurant.
· All parking spaces shall be perpendicular to the traffic aisles.
· No parallel parking is permitted.

9. Draw all traffic aisles and drives required to connect parking to the street.
· Drive-through circulation is required.
· Dead-end parking is prohibited.
· All drives and traffic aisles are automatically drawn at a width of 24 ft.
· The intersection of the access drive with the street must be perpendicular to the street[size=]for at least the first 20 ft of the drive.

10. Provide only one curb cut along Academy Street, located no closer than 120 ft from the intersection of the centerlines of the two existing public streets.

11. Draw vehicular circulation to access the parking and service entrance.
· A service drive shall attach to the service entrance of the Restaurant.
· A turnaround or drive-through circulation is not required for the service drive.

12. Connect the Pedestrian Plaza, the universally accessible parking spaces, and the main entrances of the two buildings to each other and to the existing public walk with a continuous walkway system.
· The Pedestrian Plaza shall be considered part of the walkway system.
13. Adhere to the following general conditions:
· Paving on the site shall be minimized.
· Drives, traffic aisles, and parking spaces shall be no closer than 7 ft to a building.
· Buildings must be separated by a minimum of 30 ft.
· Provide a 30 ft setback from the Pond for all construction or built improvements.
· No more than 8 existing trees may be removed or disturbed.
· No construction or built improvements of any kind shall occur over any other existing site feature.
· No construction or built improvements of any kind shall occur outside the building limit line except for direct vehicular and pedestrian access.
· Buildings shall not overlap the Pedestrian Plaza or parking.
You do not have the required permissions to view the files attached to this post.
Veronika
 
Posts: 28
Joined: Tue Mar 05, 2013 4:04 pm

Re: here's my solution for the alt. site program #3

Postby raustin1011 » Fri Apr 20, 2018 8:20 pm

My thoughts, i am studying for this now too, so not an expert:

I don't think that you are providing adequate shade for the Plaza, a Conifer only will cast 50' and Restaurant 36'. I would say greater than 50% of your plaza is in direct sunlight, which seems like a high tolerance to expect. Your standard parking spaces must traverse either landscaped area or a fair amount of road, I would want a better pedestrian connection.
raustin1011
 
Posts: 24
Joined: Tue Jul 07, 2015 1:07 pm

Re: here's my solution for the alt. site program #3

Postby Veronika » Sat Apr 21, 2018 6:21 am

Thanks for your input
Veronika
 
Posts: 28
Joined: Tue Mar 05, 2013 4:04 pm


Return to SPD - SITE PLANNING & DESIGN

Who is online

Users browsing this forum: No registered users and 56 guests