First stab at Site Grading. One with sketch lines and one without. Made sure to check I didn't have greater than 50' point to point using a sketch line and no closer than 5' using sketch circles. Thanks in advance.
Regards
malexisp wrote:Good Afternoon Tesser2,
I thought about bringing the 108 contour points closer together, but the slope between 108 and 107 would have exceeded 2% I believe.
Based on the program "The slope of the regraded portions of the site shall be at least 2% and no more than 20%"
I used the formulas:
1'/2%= 50'
1'/20%=5'
Thanks for your review and comments.
malexisp wrote:true.
Btw. Is there a rule of thumb for how close the distance between the two contour points should be?
Thanks again Sparky