Delivery Methods

Site Zoning Vignette and Multiple Choice

Delivery Methods

Postby LL101 » Fri May 12, 2017 1:17 pm

Which delivery method will provide the client with the project cost at an earlier time?
-Design build?
-Design bid build?
-Fast Track?
LL101
 
Posts: 4
Joined: Mon Mar 13, 2017 6:33 am

Re: Delivery Methods

Postby greek22 » Sat May 13, 2017 12:45 pm

CM @ Risk will provide the client with the project cost at the earliest time.

However if thats not an option, my guess would be Design/Build - it allows for earlier knowledge of cost.
Last edited by greek22 on Tue May 29, 2018 7:00 pm, edited 1 time in total.
greek22
 
Posts: 312
Joined: Sat Nov 22, 2014 3:10 pm

Re: Delivery Methods

Postby chrisschumm » Mon May 15, 2017 7:15 am

Get your hands on the AIA handbook for professional practice, they explain delivery methods 100% better than kaplan... I found one on ebay for 60$ and that book i will keep as its got a ton of great info... my bosses at work have borrowed it already lol!
chrisschumm
 
Posts: 40
Joined: Wed Mar 22, 2017 7:29 am

Re: Delivery Methods

Postby LL101 » Tue May 16, 2017 3:33 pm

I would think that the design/build method would provide the cost the earliest because the design/build entity will bid the project before starting development.
LL101
 
Posts: 4
Joined: Mon Mar 13, 2017 6:33 am

Re: Delivery Methods

Postby cma52572 » Mon Feb 19, 2018 10:34 pm

yeah I think its actually design build. I think that is addressed in Black Spectacles somewhere. w/ DB you should know in pre design.
cma52572
 
Posts: 164
Joined: Sat Mar 12, 2016 5:56 pm


Return to PPP - PROGRAMMING, PLANNING & PRACTICE