"During the bid phase, the contractor hired to construct a small shopping mall planned for an 18 month construction schedule. After construction begins, the client notifies the architect that, due to financing considerations, construction must be completed three months earlier than the original date for substantial completion. The architect should recommend that the client:
A. hire a different contractor
B. reduce the scope of the project
C. replan using a Gantt schedule
D. authorize the contractor to use a fast-track schedule"
The answer is D.
I guess I need to go back and read up on fast track again, because per the question construction has already begun. I thought fast track was something planned from the outset, and you have separate bid packages etc. so that there isn't a traditional design-bid-build separation. Can fast tracking happen only during the construction phase?