Going through the ballast review sample tests. One question suggests that after construction begins, the owner could as the contractor to fast track the project for substantial change order costs.
Isn't the point of fast tracking to overlap the design and construction phases? If you have already started building, the design documents are done and bid,,,, no fast tracking for you.
Anyone agree? Disagree?
Thanks
Luke