9. During the bid phase, the contractor hired to construct a small shopping mall planned for an 18-month construction schedule. After construction begins, the client notifies the architect that, due to financing considerations, construction must be completed three months earlier than the original date for substantial completion. The architect should recommend that the client
A. Hire a different contractor
B. Reduce the scope of the project
C. Replan using a Gantt scheudle
D. Authorize the contractor to use a fast-track schedule.
The correct answer listed in Ballast is D, which I disagree with since during the bid phase the CDs have already been completed by the architect and it's too late to start the fast-track schedule. Fast-track schedules work by overlapping the design phase with the construction phase. How can you fast-track a construction schedule when the design has already been completed?
Is this another ballast-FAIL question?