Revision, Addendum, Change Order on the actual drawing

Revision, Addendum, Change Order on the actual drawing

Postby blackraider453 » Sun May 26, 2019 11:18 am

Hello! I have a question that for some reason I have become confused. I am going to make up a question but hopefully, it answers my question.

You have been asked to change the scope of work after a contract has been signed you as the architect Issue a change order. What do you put on the drawings noting these changes in work for the GC?

A. Addendum
B. Revision
C. Change Order?
D. Other?

I know you can use revision clouds before it is sent out to bidders, and you issue Addendums before the contract is signed. But on your actaul drawing what goes on it after the owner has selected a GC?
blackraider453
 
Posts: 5
Joined: Thu Mar 09, 2017 12:55 pm

Re: Revision, Addendum, Change Order on the actual drawing

Postby Coach » Sun May 26, 2019 7:31 pm

Change order and associated rev with clouded drawings and specs if applicable.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Revision, Addendum, Change Order on the actual drawing

Postby blackraider453 » Tue May 28, 2019 10:45 pm

Thank you Sir!
blackraider453
 
Posts: 5
Joined: Thu Mar 09, 2017 12:55 pm