UNIT IN PLACE ESTIMATE?

UNIT IN PLACE ESTIMATE?

Postby Bae » Mon Jan 14, 2019 8:29 pm

Hey Guys,

Does anyone know what a unit in place estimate is and what phase it would be used in??

Thanks!
Bae
 
Posts: 9
Joined: Mon Jan 14, 2019 8:27 pm

Re: UNIT IN PLACE ESTIMATE?

Postby KOOTA » Tue Jan 15, 2019 10:22 am

I have the same question and cant find it anywhere.
I took it as unit per assembly which is in DD
KOOTA
 
Posts: 110
Joined: Sun Jan 24, 2016 8:16 pm

Re: UNIT IN PLACE ESTIMATE?

Postby Bae » Wed Jan 16, 2019 10:05 pm

Still no luck :(

I did find this

Unit in place- Definition

The appraisal method of estimating building costs by calculating the costs of all of the physical components in the structure, with the cost of each item including its proper installation. Also called the segregated cost method
Bae
 
Posts: 9
Joined: Mon Jan 14, 2019 8:27 pm

Re: UNIT IN PLACE ESTIMATE?

Postby KOOTA » Mon Jan 21, 2019 10:40 am

THANK YOU, CAN SOMEONE CONFIRM THIS, so this is done at CD or bidding phase right?
KOOTA
 
Posts: 110
Joined: Sun Jan 24, 2016 8:16 pm

Re: UNIT IN PLACE ESTIMATE?

Postby EddyMelo » Sat Dec 28, 2019 8:13 am

I'd think it's during CD. Wouldn't the "cost estimate" during bid phase be the bid itself from the contractor?