CHANGES DURING DESIGN PHASES

PostPosted: Thu Jun 29, 2017 1:47 pm
by ArchiShark
Can anyone help me out with the process of client changes during the design phases. I'm guessing that any changes during a design phase that would change a major design item/element, that was already approved at end of a previous phase would trigger an additional service because the change is after client approval. OR is it only changes after design development phase approval that deserve an additional service charge? OR am I totally wrong in both cases. Please help testing soon July 26. Thanks :?:

Re: CHANGES DURING DESIGN PHASES

PostPosted: Thu Jun 29, 2017 4:21 pm
by gbalaka
The simple answer to your question is that if the client changes the scope of work during the first three phases (thus changes the contract), that would entitle the Architect to additional compensation.

Doesn't matter if it's SD, DD or CD. The important thing is that the contract is changing.

Re: CHANGES DURING DESIGN PHASES

PostPosted: Thu Jun 29, 2017 4:27 pm
by Coach
Look at the contract. Be sure to study the version with commentary.

Re: CHANGES DURING DESIGN PHASES

PostPosted: Fri Jun 30, 2017 5:34 pm
by ArchiShark
Will Do! Thank you for pointing me in the right direction coach.

Re: CHANGES DURING DESIGN PHASES

PostPosted: Fri Jun 30, 2017 6:34 pm
by ArchiShark
Thanks Gbalaka, I see the repeated calls for client approvals now, B210 2.2.4, 2.2.7, 2.3.1, 2.3.3, 2.4.1. Helpful!