- Anytime : O stops W or ends Ctract w/ A
- 4d : no more Addenda to Bid Date
- 7d : A to certify App4Pymt & forward to O
- 7d : Sub/Sup stops W if non-pay from GC
- 7d+7d* : GC stops W if non-pay beyond scheduled pay date
- 10d : Bid advertising prior to Bid Date
- 10d : GC to submit App4Pymt to A
- 10d : notice to GC before O carries out own force
- 14d : O furnishes Lien related Info to GC
- 14d : A+O subject to Sub qualification
- 15d : A+O subject to Superintendent
- 15d : O to file NOC
- 15d : O to forward Lien Info/Claim to A
- 20d : Sub/Sup to serve Lien Right Notice
- 20d : GC/Sub/Sup to serve Stop Pymt Notice
- 20d : Pub Review period for Negative Declaration
- 21d : file Claim to IDM
- 21d : GC to claim unknown site discovery
- 30d : Pub Review of Draft EIR
- 30d : A to report CAB requests
- 30d : Sub/Sup to file Lien if NOC is filed
- 30d+7d* : GC terminate W after GOV caused delay
- 45d : Pub Review of Draft EIR if SCH involved
- 60d : for GC to file Lien if NOC is filed
- 60d : lag time for A to end CAdmin after SComp shall FPymt Date is delayed.
- 90d : for GC to file Lien if NOC is not filed
- 90d : Const Cost be adjusted after CD submitted
- 90d+7d* : A ends Ctract if O delays
- 120d+7d* : GC stops W if W delayed by O
- 1yr : correction period after SComp or repose.
- 1yr : max jail time for holding out as A
- 2yrs : land-subdivision process
- 2yrs : license fee circle
- 4yrs : patent warranty ends
- 5yrs : license expires
- 5yrs : State water plan update circle
- 10yrs : latent warranty ends
- 10yrs+1d : A to trash project record
---------------------------------------------------------------------
Did I miss anything ?