Postby zrh2103 » Tue Mar 28, 2017 8:00 pm

In David's Flash Card. It says Excluding the drawing, what two documents are part of the bid document but not part of the project manual?
1. Invitation to Bidders/ Instructions to Bidders
2. Form of Agreement between owner and contractor.

The second one is not true because A101 should be part of the project manual.


From what i understood, project manual consists of the followings:

Invitation to bid
Instruction to Bidders
Info available to Bidders
Pre qualification form
Bid Form and attachment
bid Security
Owner and Contractor Agreement (A101)
Performance bond and Payment bond (A312)
Certificates of insurance
General Conditions (A201)
Supplementary Conditional (A511)
Specifications
zrh2103
 
Posts: 129
Joined: Thu Sep 12, 2013 9:20 pm

Re: Project Manual

Postby Coach » Tue Mar 28, 2017 8:54 pm

Drawings & addenda.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Project Manual

Postby adventurer4hire » Tue Mar 28, 2017 8:58 pm

David is clearly wrong. Take a look at this graphic. I used this when I was in school, it is slightly old, but I think it still applies. If I am wrong, someone let me know, but I think the correct answer to the question is: Addenda and Contract Modifications.
You do not have the required permissions to view the files attached to this post.
adventurer4hire
 
Posts: 132
Joined: Sat Sep 14, 2013 4:37 pm
Location: San Jose

Re: Project Manual

Postby Coach » Tue Mar 28, 2017 9:02 pm

adventurer4hire wrote:David is clearly wrong. Take a look at this graphic. I used this when I was in school, it is slightly old, but I think it still applies. If I am wrong, someone let me know, but I think the correct answer to the question is: Addenda and Contract Modifications.

Contract modifications are not part of bid docs.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Project Manual

Postby zrh2103 » Wed Mar 29, 2017 4:45 am

adventurer4hire wrote:David is clearly wrong. Take a look at this graphic. I used this when I was in school, it is slightly old, but I think it still applies. If I am wrong, someone let me know, but I think the correct answer to the question is: Addenda and Contract Modifications.



Coach is right. Drawing and addenda. You cant bid on change orders, change directives and ASIs. Bidders have no way to know that in advance as how many changes will be in the future. And also no one is issuing any contract modification during bidding phase.
zrh2103
 
Posts: 129
Joined: Thu Sep 12, 2013 9:20 pm

Re: Project Manual

Postby adventurer4hire » Wed Mar 29, 2017 6:59 am

Thanks! I was just making sure people were paying attention...
adventurer4hire
 
Posts: 132
Joined: Sat Sep 14, 2013 4:37 pm
Location: San Jose