Woo’s question #62

PostPosted: Mon May 09, 2016 12:12 pm
by chillout
Q. Which of the following are required to be provided by the Owner to the Contractor at the start of construction?
A. financial information in regards to liens
B. survey of the site
C. testing services for code required testing of construction methods
D. service of a qualified inspector on site at all times to inspect construction

Correct answers : A,B & C

Can anyone verify if C is required of the Owner?

Re: Woo’s question #62

PostPosted: Mon May 09, 2016 1:52 pm
by Coach
A201.13.5.

Re: Woo’s question #62

PostPosted: Mon May 09, 2016 2:22 pm
by chillout
Thanks very much Coach. I appreciate the clarification.

Re: Woo’s question #62

PostPosted: Mon May 31, 2021 5:47 pm
by cashew
I am confused by Woo's answer... Why is D left out? Doesn't the Owner also pay for the "service of a qualified inspector on site at all times to inspect construction"? Is this option left out because the inspector is not provided at the "start of construction"? (But if that's the reasoning, I still don't understand, since this inspector is on site at all times, presumably from the very beginning).

Woo's answer key even says "Even if D is required they need to be contracted directly with the Owner." - so why wouldn't D be included in the correct answer?