If the architect doesn't respond to submittal...

Building Section Vignette and Multiple Choice

If the architect doesn't respond to submittal...

Postby anonymous283 » Wed Apr 04, 2018 12:00 pm

I remember a practice test question saying something along the lines that if an architect doesn't respond to a submittal in x days, the contractor considers the submittal approved. I can't find the question and maybe I'm wrong but is this true and how many days? Would that contradict the statement in a201 about responding just with reasonable promptness with no time limit?
anonymous283
 
Posts: 149
Joined: Thu Jan 11, 2018 2:02 pm

Re: If the architect doesn't respond to submittal...

Postby thd7t » Wed Apr 04, 2018 12:24 pm

Reasonable time for review is what A201 says and what governs in this case.

In practice, it is true that 10 working days is considered reasonable time for most submittals, though.
thd7t
 
Posts: 400
Joined: Mon Aug 22, 2016 1:23 pm

Re: If the architect doesn't respond to submittal...

Postby Coach » Wed Apr 04, 2018 1:36 pm

anonymous283 wrote:I remember a practice test question saying something along the lines that if an architect doesn't respond to a submittal in x days, the contractor considers the submittal approved.

Nope. Read A201.3.12.7.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am