Standard Order of Drawings and Consultant Drawings

Building Section Vignette and Multiple Choice

Standard Order of Drawings and Consultant Drawings

Postby greenHandle23 » Fri Feb 16, 2018 2:19 pm

The Kaplan study material says that the consultants drawings (the way that they are organized in a set) = P, M, E. Plumbing, Mech, and Elec.
The "Caroline Notes" states this another way on Page 11 of 60 = M, P, E.

So, does anyone have an idea of what the CDS test will look for on the correct answer to this question for standard order of drawings and consultant drawings within a set?
greenHandle23
 
Posts: 7
Joined: Mon Dec 15, 2014 8:29 pm

Re: Standard Order of Drawings and Consultant Drawings

Postby Coach » Fri Feb 16, 2018 2:36 pm

PME is correct as far as I'm concerned, but see if AHPP has anything to say about it.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Standard Order of Drawings and Consultant Drawings

Postby fare75 » Wed Feb 21, 2018 2:53 am

Coach wrote:PME is correct as far as I'm concerned, but see if AHPP has anything to say about it.

I can confirm this from this diagram from Architectural Graphics Standards
(Lowest is on top...poor graphic presentation :roll: )

Drawing_Order.JPG
You do not have the required permissions to view the files attached to this post.
fare75
 
Posts: 195
Joined: Sun Mar 22, 2015 10:35 am

Re: Standard Order of Drawings and Consultant Drawings

Postby Coach » Wed Feb 21, 2018 12:06 pm

fare75 wrote:I can confirm this from this diagram from Architectural Graphics Standards

That also shows S before A, which is ridiculous.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am


Return to CDS - CONSTRUCTION DOCUMENTS & SERVICES

Who is online

Users browsing this forum: No registered users and 9 guests

cron