Page 1 of 1
A201 General Conditions
Posted:
Mon Feb 05, 2018 9:49 pm
by mmartric
Which of the following is included in the A201 General Conditions?
Field Order
Post bid modifications
Test Boring Logs
Bid Bond
Re: A201 General Conditions
Posted:
Wed Feb 07, 2018 1:05 pm
by anonymous283
None?
Re: A201 General Conditions
Posted:
Wed Feb 07, 2018 4:32 pm
by Coach
Only one is mentioned in A201. You might want to read it.
Re: A201 General Conditions
Posted:
Wed Feb 07, 2018 6:39 pm
by Sparky83
Coach wrote:Only one is mentioned in A201. You might want to read it.
Don't take the exam unless you have....
Re: A201 General Conditions
Posted:
Mon Mar 26, 2018 2:45 pm
by jbmadison
Hello,
I have read the A201 General Conditions document, taken notes and reviewed them but cannot answer this question. Can anyone shed light on the answer?
Thanks in advance!
Re: A201 General Conditions
Posted:
Mon Mar 26, 2018 9:48 pm
by Coach
1.1.1
Re: A201 General Conditions
Posted:
Tue Mar 27, 2018 10:58 am
by jbmadison
Got it, thank you. Change orders, Construction Change Directives, and a written order for minor change of work are all Post Bid Modifications. Seems obvious now...