Which of the following is included in the A201 General Conditions?

Field Order
Post bid modifications
Test Boring Logs
Bid Bond

Re: A201 General Conditions

PostPosted: Wed Feb 07, 2018 1:05 pm
by anonymous283
None?

Re: A201 General Conditions

PostPosted: Wed Feb 07, 2018 4:32 pm
by Coach
Only one is mentioned in A201. You might want to read it.

Re: A201 General Conditions

PostPosted: Wed Feb 07, 2018 6:39 pm
by Sparky83
Coach wrote:Only one is mentioned in A201. You might want to read it.

Don't take the exam unless you have....

Re: A201 General Conditions

PostPosted: Mon Mar 26, 2018 2:45 pm
by jbmadison
Hello,
I have read the A201 General Conditions document, taken notes and reviewed them but cannot answer this question. Can anyone shed light on the answer?
Thanks in advance!

Re: A201 General Conditions

PostPosted: Mon Mar 26, 2018 9:48 pm
by Coach
1.1.1

Re: A201 General Conditions

PostPosted: Tue Mar 27, 2018 10:58 am
by jbmadison
Got it, thank you. Change orders, Construction Change Directives, and a written order for minor change of work are all Post Bid Modifications. Seems obvious now...