Bad kaplan question?

Building Section Vignette and Multiple Choice

Bad kaplan question?

Postby anonymous283 » Mon Feb 05, 2018 4:46 pm

Please see attached images. The answer is supposedly C, to terminate the contract. I answered A because of 9.1... The reasoning Kaplan gives is that the owner could claim damages if the architect withholds services. Which one is it?
You do not have the required permissions to view the files attached to this post.
anonymous283
 
Posts: 149
Joined: Thu Jan 11, 2018 2:02 pm

Re: Bad kaplan question?

Postby Coach » Mon Feb 05, 2018 5:20 pm

C is correct.
If A mentioned the 7 day notice, then A and C would be equally correct.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Bad kaplan question?

Postby anonymous283 » Wed Feb 07, 2018 1:03 pm

Coach wrote:C is correct.
If A mentioned the 7 day notice, then A and C would be equally correct.

ugh fair enough. Thanks.