Bad kaplan question?

PostPosted: Mon Feb 05, 2018 4:46 pm
by anonymous283
Please see attached images. The answer is supposedly C, to terminate the contract. I answered A because of 9.1... The reasoning Kaplan gives is that the owner could claim damages if the architect withholds services. Which one is it?

Re: Bad kaplan question?

PostPosted: Mon Feb 05, 2018 5:20 pm
by Coach
C is correct.
If A mentioned the 7 day notice, then A and C would be equally correct.

Re: Bad kaplan question?

PostPosted: Wed Feb 07, 2018 1:03 pm
by anonymous283
Coach wrote:C is correct.
If A mentioned the 7 day notice, then A and C would be equally correct.

ugh fair enough. Thanks.