Bad kaplan question?
Posted: Mon Feb 05, 2018 4:46 pm
Please see attached images. The answer is supposedly C, to terminate the contract. I answered A because of 9.1... The reasoning Kaplan gives is that the owner could claim damages if the architect withholds services. Which one is it?