Does A201 extend responsibilities from owner to consultant?

Building Section Vignette and Multiple Choice

Does A201 extend responsibilities from owner to consultant?

Postby anonymous283 » Sat Feb 03, 2018 9:40 am

I have study material that tells me a201 extends rights and responsibilities from owner to contractor to subcontractor and from owner to architect to consultant (thats it - it does not say it can do this; it just says a201 does this). I got the following practice question: An Architect contracts with a Structural Engineer to provide structural engineering services for a project. Who is responsible to the Owner for the adequacy of the structural system? I answered architect and engineer because of that study material. The answer was just architect. I searched the a201 contract for the word consultant and read every instance. Not once does it describe extending rights and responsibilities. So is my study material wrong?
anonymous283
 
Posts: 149
Joined: Thu Jan 11, 2018 2:02 pm

Re: Does A201 extend responsibilities from owner to consulta

Postby Coach » Sat Feb 03, 2018 3:23 pm

Subs and consultants must abide by the terms of the primary contract; however, contractual responsibility can only be between parties to the contract.
User avatar
Coach
Site Admin
 
Posts: 13249
Joined: Wed May 23, 2012 2:08 am

Re: Does A201 extend responsibilities from owner to consulta

Postby anonymous283 » Sun Feb 04, 2018 12:28 pm

thank you coach
anonymous283
 
Posts: 149
Joined: Thu Jan 11, 2018 2:02 pm