A question regarding cost estimate

Building Section Vignette and Multiple Choice

A question regarding cost estimate

Postby DYARCHITECT » Sat Jan 27, 2018 9:09 pm

A question on Designerhack.
In which two phases is subsystem estimate method usually used?
The answer is SD and DD. I think it should be DD and CD. Am I right or not?
Thanks.
DYARCHITECT
 
Posts: 23
Joined: Tue May 10, 2016 12:37 pm

Re: A question regarding cost estimate

Postby thd7t » Mon Jan 29, 2018 6:32 am

By the time you get to CDs, you should be beyond a subsystems estimate.
thd7t
 
Posts: 400
Joined: Mon Aug 22, 2016 1:23 pm

Re: A question regarding cost estimate

Postby DYARCHITECT » Wed Jan 31, 2018 6:57 pm

Thank you!

thd7t wrote:By the time you get to CDs, you should be beyond a subsystems estimate.
DYARCHITECT
 
Posts: 23
Joined: Tue May 10, 2016 12:37 pm