Page 1 of 1

Question on B101 Section 6.7

PostPosted: Sat Jan 13, 2018 4:22 pm
by an9e1an
Base on B101 Section 6.7, arch is to revise CD at no additional cost at the conclusion of CD phase. What if the owner decided to change budget or project scope during the construction phase or later? Since the owner is reversing on previously approved documentation (section 4.3.1.1), the arch is entitled to additional services compensation, right?