Page 1 of 1

3.1 - First Attempt TEST TOMORROW

PostPosted: Sun Dec 17, 2017 4:46 pm
by nicolenalvarez
It's last minute, but thought I'd post just in case someone saw before the end of the night. I test in the morning. Appreciate any feedback.

thank you

Re: 3.1 - First Attempt TEST TOMORROW

PostPosted: Sun Dec 17, 2017 5:36 pm
by nicolenalvarez
I caught a mistake. I had calculated the amount of space needed for the duct/joist of the 1st floor correctly but made an error while drawing it. Glad I'm getting in plenty of practice with this lousy software...

Re: 3.1 - First Attempt TEST TOMORROW

PostPosted: Sun Dec 17, 2017 9:44 pm
by Charndc
I would check the duct work shown on the 2nd floor. I am getting that the duct work should be 32 x 16 at the cut line, same as the first floor, and your ducts appear to be different sizes.

Good luck,