4.0 Vig First Attempt

Building Section Vignette and Multiple Choice

4.0 Vig First Attempt

Postby rebeccapants » Sat Nov 11, 2017 4:48 pm

I think I know some potential mistakes:

1. I sized the lab ceiling space to accommodate the largest duct on the entire 2nd floor, but now I think it just had to be the largest duct size in the lab room, since the ceiling heights are different. Is that correct?

2. Some have mentioned non-rated interior partitions must go 6" above the ceiling. Is that true that the vignette is scored that way?

Any other issues?

Many thanks.

Screen Shot 2017-11-11 at 6.29.21 PM.png
You do not have the required permissions to view the files attached to this post.
rebeccapants
 
Posts: 15
Joined: Sat Jul 30, 2016 7:10 pm

Re: 4.0 Vig First Attempt

Postby thd7t » Mon Nov 13, 2017 1:18 pm

rebeccapants wrote:I think I know some potential mistakes:

1. I sized the lab ceiling space to accommodate the largest duct on the entire 2nd floor, but now I think it just had to be the largest duct size in the lab room, since the ceiling heights are different. Is that correct?

2. Some have mentioned non-rated interior partitions must go 6" above the ceiling. Is that true that the vignette is scored that way?

Any other issues?

Many thanks.

Screen Shot 2017-11-11 at 6.29.21 PM.png

I only see the two issues that you referenced. You can get an idea of the vignette's scoring by watching NCARB's video. They do want the non-rated partition to go 6" above ceiling.
thd7t
 
Posts: 400
Joined: Mon Aug 22, 2016 1:23 pm


Return to CDS - CONSTRUCTION DOCUMENTS & SERVICES

Who is online

Users browsing this forum: No registered users and 23 guests