When does a project specific information belong to Special Condition vs. Division 01?
and vs. Supplementary Conditions?
At the end of Kaplan, there is a list of Examples of Special Conditions, many of the what is listed there appear to be Division 01 items to me, so i want to ask....
for example:
1. "Job Sign: Furnish and erect two 96"x96" job signs painted and lettered to identify Project, The Owner, the Architect, the Contractor, and four Consulting Engineers."
2. "5 copies of material lists, schedules and brochures as required under various sections shall be submitted to Architect for approval"
What if there are such conditions with the project:
3. If site is located adjacent to a mountain that would rush rainwater from the mountain onto the site and contractor should be prepared of potential flooding during construction
4. access to site is only allowed between 10am-12pm and 2pm-4pm weekdays. Weekends access is not allowed.
5. project is located in Shenzhen, however, if there is disagreement, arbitration will be carried out in Hong Kong
which one belongs to Supplementary condition, Division 01 or Special Condition?
Can someone be so kind to provide an explanation please?