Hello!

This is my first pass at 3.1 and it definitely makes you think a little more than 4.0.

My questions, please verify if this is correct thinking with regard to duct clearances:

1st Floor:
It looks like the deepest duct is 24", so 24" + 8" clearance = 32" needed from finish ceiling to bottom chord of trusses, correct?

2nd Floor:
Deepest duct is again 24", so 32" again needed from finish ceiling to bottom chord of trusses.

Meeting Room
It looks like there is a riser duct leading in that is 32x12, then the 12" depth + 8" clearance = 20" to bottom chord of truss from ceiling finish.

Thanks!
You do not have the required permissions to view the files attached to this post.
User avatar
oneonth3run
 
Posts: 33
Joined: Sun Jan 31, 2016 5:10 pm

Return to CDS - CONSTRUCTION DOCUMENTS & SERVICES

Who is online

Users browsing this forum: No registered users and 40 guests

cron