FEW QUESTIONS OF COURSE:
1)frost line is @ 5', do I draw " foundation with footing" @ 6' assuming that the footing is 1'x3' ( program doesn't' give sizes)?
2) intersect bearing wall with slab? or do I penetrate the wall with the slab by a few clicks?
3) ceiling stops at each wall (stops at bearing walls) or can it go through partition walls ?
4)footing for the interior wall goes directly under the slab, but does it need a steam wall at all or the bearing wall sits directly on top of the footing without a steam?
5)where do you start drawing the section? up, down or place my ground line directly on top of the section line? ( does it matter)
6) how many inches into the bearing wall with truss elevation?
7)total 2nd floor T+D depth is 3'8" ????
8) 29'10" T.O.P ?