by gbalaka » Sat May 20, 2017 10:59 am
I'm looking at the A201, section 9.9 PARTIAL OCCUPANCY OR USE and i've read it several times and i'm not sure how to interpret it.
....Such partial occupancy or use
may commence whether or not the portion
is substantially complete, provided
the Owner and Contractor have accepted
in writing the responsibilities assigned to
each of them for payments, retainage, if
any, security, maintenance, heat, utilities,
damage to the Work and insurance, and
have agreed in writing concerning the
period for correction of the Work and
commencement of warranties required
by the Contract Documents.....
How do you interpret that Coach?
It almost seems that the answer is between the owner and the contractor? I'm not understanding this clearly.