when there is a discrepancy

PostPosted: Wed Mar 29, 2017 7:26 pm
by pig
hi all, wondering if.....
when there is a discrepancy between contract drawings and specifications, drawings take precedence right?
what if there is a discrepancy between the AIA documents say between agreement and supplementary conditions or general conditions?
thanks!

Re: when there is a discrepancy

PostPosted: Thu Mar 30, 2017 10:54 am
by Coach
pig wrote:when there is a discrepancy between contract drawings and specifications, drawings take precedence right?

Nope.

what if there is a discrepancy between the AIA documents say between agreement and supplementary conditions or general conditions?

See A201 w/commentary -- 1.2.1 & 3.2.2

Re: when there is a discrepancy

PostPosted: Mon Apr 17, 2017 6:05 am
by fliparch
They are both binding.

What if a jobsite calls to clarify a detail that shows a vinyl base for a Historic Building renovation you're working on, when you really meant wood which the Specs indicate (or vice versa)?

pig wrote:hi all, wondering if.....
when there is a discrepancy between contract drawings and specifications, drawings take precedence right?
what if there is a discrepancy between the AIA documents say between agreement and supplementary conditions or general conditions?
thanks!

Re: when there is a discrepancy

PostPosted: Mon Apr 17, 2017 6:41 am
by corbismyhomeboy
"Drawings and specifications are complementary and what is called for by one shall be as binding as if called for by both." <- I have this on a post-it on my desk to remind me that they are interdependent and therefore both deserve the same amount of attention! It's easy to prioritize the drawings, but specs are important too!

fliparch wrote:What if a jobsite calls to clarify a detail that shows a vinyl base for a Historic Building renovation you're working on, when you really meant wood which the Specs indicate (or vice versa)?

I know you were using this as an example, fliparch! If you have a decent contractor, they should notice the discrepancy and ask for clarification in an RFI. A lot of contractors aren't so decent though so it's obviously a good thing to give your spec writer the most up-to-date drawings and keep him/her in the loop about project decisions. Our spec writer is very good about being specific about the language used so we can edit the language in the drawings to match the specs to minimize confusion.

Re: when there is a discrepancy

PostPosted: Thu Nov 02, 2017 7:48 am
by pig
thank you so much everyone for your response!
so Ballast was wrong!!
it says " When there is a conflict between the drawings and the specs, the courts have held that the specs are more binding and take precedence over the drawings"
Kaplan says both binding according A201 1.2.1 and 4.2.11

Re: when there is a discrepancy

PostPosted: Tue Nov 07, 2017 1:53 am
by cma52572
damn, Ive always thought the specs ruled. the study material for CDs is AWFUL! it all conflicts.

Re: when there is a discrepancy

PostPosted: Sat Nov 18, 2017 8:00 pm
by pig
cma52572 wrote:damn, Ive always thought the specs ruled. the study material for CDs is AWFUL! it all conflicts.

A201 is always the best to follow!