Coach/ All,
For the CDS vignette, appreciate your comments on the following:
1. Is it correct to place the slab on grade above the grade line?
2. is it correct to have the exterior bearing walls to the bottom of SOG and foundation wall below it?
3. is it correct to continue finish ceiling thru the rated wall or should it break?
4. should duct/s be exactly below the joists, touching the bottom of the joist?
5. slab on grade to break at bearing walls, correct?
6. rated wall to break at the bottom of floor slab?
Thanks for your help!